Severodvinsk nuclear-powered submarine "Severodvinsk" (November 9, 2014) [credit: TASS] |
Are these numbers and timelines real?
Construction of the first (and only) Project 885 hull, "Severodvinsk", took 20 years from keel-laying to delivery. During that time, requirements were changed and new design specifications were implemented. The second unit, "Kazan", was laid down in July 2009 and is being built under the improved Project 885M design. Initial reporting indicated "Kazan" would be delivered in 2014. The delivery date, however, began slipping into 2015, 2016, and now 2017. A 2017 delivery would equate to eight years since the hull was laid - a lot better than 20 years.
After reviewing equipment delivery schedules, the actual timelines for only seven units looks something like this:
HULL | NAME | LAID | LAUNCHED | DELIVERED |
160 | Severodvinsk | Dec 1993 | Jun 2010 | Dec 2013 |
161 | Kazan | Jul 2009 | (2016) | 4Q2017 |
162 | Novosibirsk | Jul 2013 | (2019) | |
163 | Krasnoyarsk | Jul 2014 | (2019) | |
164 | (2015) | (2020) | ||
165 | (2015) | (2021) | ||
166 | (2015) | (2022) |
Unless SevMash production and contractor-supplied equipment deliveries can be sped up, delivering more than five submarines by the end of 2020 appears improbable.